Small hydro power station Feßnachbach II

Construction of a diversion plant on the Feßnachbach river in the towns of St. Lorenzen bei Scheifling and Scheifling (Murau district, Styria).

HEP operators E-Werk Feßnach GmbH planned the construction of a small hydro power plant and commissioned PI Mitterfellner with approval and implementation planning, detailed planning and overall management of this project.

This small hydro power station has been designed as a diversion plant. Process water is drawn from the Feßnachbach river in the town of St. Lorenzen bei Scheifling. The motive water is returned into the Mur river in the town of Scheifling. The generated energy is fed into the local utility company’s mains grid.

Client and operator:
E-Werk Feßnach GmbH

Service period:
2010 – 2011

Leaflet (German language):
KW Feßnachbach II